NHPC shuts 120 MW plant in J-K till March ’21

State-run hydro power giant NHPC on Wednesday said its 120 MW Sewa-II power station in Jammu and Kashmir has been shut till March 31, 2021 due to some damage in its head race tunnel (HRT). The HRT carries water from intake to a power house for electricity generation.

“It is to inform that Sewa-II Power Station (120 MW) in UT of Jammu & Kashmir has been under complete shutdown w.e.f. 25.09.2020 to 31.03.2021 for damage of HRT,” the company said in a BSE filing.

The shutdown will cause tentative loss of 157.4 MUs (million units) in generation (design energy) and 35.61 per cent in NAPAF (Normative Annual Plant Availability Factor), it added.