NTPC synchronises one more unit of 3,300 megawatt power plant in Bihar with grid

State-run NTPC Ltd on Sunday said it has successfully synchronised a 660-MW unit of its supercritical thermal power plant in Bihar with the grid, which would help the commercial generation of electricity from it. The power producer has been setting up five units with 660 MW capacity each, spread across 3,200 acres of land at Barh in Patna district.

The construction work of three units of stage-I of the project was delayed due to “contractual, execution and timeline issues” with Russian firm Technoprom Export which was supposed to develop them, while two units of stage-II (2×660 MW) of Barh STPP have already been commissioned and are presently under operation, an official said.

“The first unit of 660 MW of stage -I of Barh plant was successfully synchronised with the grid at 7.32 am today. The plant has achieved desired capacity,” he said.

Source
ET Energy World
Show More

Related Articles

Leave a Reply

Your email address will not be published.

Back to top button
Close
Close